Work Performed, September 5th to September 8th   
·         Work focused on the area between the railroad tracks and Pine Street on the south side of the road (adjacent to Glenview House)
o   Removed and poured concrete curb & gutter and sidewalk
o   Completed underground piping for irrigation and electrical systems.
o   Poured colored and stamped concrete sidewalk
o   Majority of work in this area is completed.
·         Poured colored and stamped concrete around Veteran’s Memorial at River Drive
·         Poured colored and stamped concrete in various medians.
·         Continued with installation of traffic signals and posts at Glenview Road and Church Street
·         Continued with irrigation and street lighting installations along project site.

Work Anticipated to be Performed, September 11th to September 15th   
·         Pour concrete sidewalk from River Drive to Church Street
·         Remove temporary stone and pour concrete driveways and sidewalks to public parking lot east of River Drive (next to Oil Lamp Theater)
·         Continue with installation of electrical and irrigation systems along project site.
·         Continue installation of new traffic signals at Church Street and Glenview Road.
·         Begin setting new light poles.
·         Complete abandonment of old water main that is no longer in service.

Next week, the concrete sidewalk and driveways for the public parking lot on the south side of Glenview Road east of River Drive (next to Oil Lamp Theater) will be poured. The parking lot will be closed starting on Monday (September 11th) and re-open by Friday (September 15th). Street parking along Glenview Road will be available during this time.

The concrete sidewalk improvements are nearly completed on the south side of Glenview Road. It is anticipated a majority of the concrete sidewalk, stamped and colored concrete sidewalk, and concrete curb & gutter replacements will be completed by the end of the next week for the entire project. The remaining concrete to be completed are those areas where the temporary street lights and temporary traffic signal poles are in conflict.

With the concrete work nearly completed, the project will be moving to the next phase, roadway resurfacing. It is anticipated roadway resurfacing will begin the week of September 18th. Roadway resurfacing will include removing the top 2-inches of the existing asphalt pavement, performing repairs to the remaining pavement as needed, and installation of a new asphalt surface. Glenview Road will remain open during this construction; however, lanes will be reduced and flaggers will be present. We do expect significant travel delays, so please plan accordingly.

Thanks for your understanding and patience.