Friday, July 21, 2017

Concrete Sidewalk on North Side of Glenview Road Continues.


Work Performed, July 17th to July 21st  
·         Removed sidewalk on the north side of Glenview Road from Church Street to bridge
·         Poured standard concrete sidewalk on the north side of Glenview Road from Pine Street to Bridge
·         Installed irrigation piping
·         Install electrical conduit and began setting concrete posts for street lighting.

Work Anticipated to be Performed, July 24th to July 28th
·         Pour sidewalk, driveway, and curb & gutter in front of OLPH parking lot (one entrance only)
·         Continue to pour standard concrete sidewalk on the north side of Glenview Road from Church Street to bridge
·         Remove sidewalk, driveways, and curb & gutter as needed on east side of Pine Street
·         Pour sidewalk, driveways, and curb & gutter as needed on east side of Pine Street (one entrance will remain open at all times)
·         Complete storm sewer work
·         Remove and pour half the driveway near Jimmy John’s / Shoppers Row parking lot
·         Continue with irrigation piping installation
·         Continue with electrical conduit installation for street lighting
·         Pour concrete bases for street lights.

Thank you to all the business owners and patrons while accessing the businesses along Glenview Road during the construction.  The Village is committed to minimizing any inconvenience to the greatest extent possible.

Friday, July 14, 2017

Concrete Sidewalk Replacement Continues on North Side of Glenview Road from Pine Street to Bridge

Work Performed, July 10 – July 14:  
·           Removed sidewalk along business front on north side of Glenview Road from Pine Street to Church Street
·           Poured concrete sidewalk up to select business fronts on the north side of Glenview Road from Pine Street to Church Street

Work Anticipated to be Performed, July 17 – July 21
·           Remove old sidewalk on the north side of Glenview Road from Pine Street to Church Street
·           Access to businesses will be maintained with ramps and gravel walkway
·           Install unit duct and irrigation system
·           Once unit duct and irrigation installation is complete, pour new sidewalk, weather permitting
·           Remove and replace sidewalk on the east side of Church Street from Glenview Road to the alley
 
Thanks again for all your patience and understanding as you navigate through the construction zone and accommodate the work being performed.