Work Performed, July 31st to August 11th  
·         Poured concrete driveways, standard sidewalk, stamped and colored concrete, and curb & gutter along the north side of Glenview Road from Pine Street to Waukegan Road.
·         Installation of underground conduit, and pole bases for street lighting
·         Installation of underground conduit, and pole bases for new traffic signals at Glenview Road & Church Street
·         Installed irrigation piping
·         Complete underground storm sewer improvements.
·         General clean-up on the north side of Glenview Road.

Work Anticipated to be Performed, August 11th to August 18th  
·         Complete a majority of the standard concrete sidewalk, colored and stamped concrete, and curb & gutter on the north side of Glenview Road from the railroad tracks to Waukegan Road
·         Complete underground conduit installation and light pole bases for new street lights on the north side of Glenview Road
·         Complete underground irrigation piping on the north side of Glenview Road
·         Perform general clean-up of landscape planting beds and rough grade areas to be sodded in the future.
·         Remove debris from storage areas on the north side of Glenview Road
·         Begin concrete sidewalk removals on the south side of Glenview Road from Waukegan Road to bridge.
·         Begin underground electrical installations on the south side of Glenview Road.
·         Begin underground irrigation piping on the south side of Glenview Road.

Work this week will focus on getting the north side of Glenview Road completed and cleaned-up prior to the start of school for OLPH.  The contractor will remove the debris and level the landscape areas to the greatest extent possible to provide a walk-way for the students. Some areas will not be 100% completed due to location of temporary signals and other work that will be performed later in the project.

The contractor is expected to begin work on the south side of Glenview Road this week as well. The contractor will focus on the area from Waukegan Road to the bridge.

Thank you to all the business owners and residents along the north side of Glenview Road as you dealt with the inconvenience of construction on-going in front of your business. We will do everything possible to minimize the inconveniences to those business owners and residents on the south side of Glenview Road as construction progresses.