Friday, July 14, 2017

Concrete Sidewalk Replacement Continues on North Side of Glenview Road from Pine Street to Bridge

Work Performed, July 10 – July 14:  
·           Removed sidewalk along business front on north side of Glenview Road from Pine Street to Church Street
·           Poured concrete sidewalk up to select business fronts on the north side of Glenview Road from Pine Street to Church Street

Work Anticipated to be Performed, July 17 – July 21
·           Remove old sidewalk on the north side of Glenview Road from Pine Street to Church Street
·           Access to businesses will be maintained with ramps and gravel walkway
·           Install unit duct and irrigation system
·           Once unit duct and irrigation installation is complete, pour new sidewalk, weather permitting
·           Remove and replace sidewalk on the east side of Church Street from Glenview Road to the alley
 
Thanks again for all your patience and understanding as you navigate through the construction zone and accommodate the work being performed.   

Friday, July 7, 2017

Construction Work Continues

Illinois legislators have passed a state budget, allowing construction of Glenview Road Streetscape Project to resume. Contractors will arrive onsite on Monday, July 10, 2017 and begin construction at 7:00 a.m.

In the next construction phase, the Contractor will be working to remove and replace the sidewalk on the north side of Glenview Road from Pine Street to Waukegan Road, then on the south side of Glenview Road from Waukegan Road to Church Street. Improvements also include irrigation system improvements; new street lighting; improved landscaping; stamped and colored concrete; traffic signal upgrades, and roadway repaving.

Coordination with business owners during construction is our highest priority. If you have any questions or concerns regarding the Glenview Road Streetscape Project, please feel free to contact Public Relations Representative Joanna Ptasinski at 815-444-3307 or jptasinski@glenview.il.us