Pavement Milling Completed. Patching to be performed Next Week

Work Performed, September 18th to September 22nd  
·         Milled existing pavement along project site.
·         Installed temporary pavement marking to delineate lanes.
·         Completed water main repairs previously identified
·         Performed cleaning and sealing of stamped concrete.
·         Irrigation piping and nozzle installation.

Work Anticipated to be Performed, September 25th to September 29th  
·         Evaluate pavement for locations to be patched
·         Perform pavement patching at locations of failed pavement base
·         Continue cleaning and sealing stamped concrete
·         Excavation and installation of topsoil in planning beds
·         Begin installing plant material in beds.

Roadway work will continue along Glenview Road next week.  The contractor will perform patching of failed sections of roadway. Once the pavement patching is completed, the first layer of asphalt pavement will be completed.  It anticipated the first layer of asphalt pavement will be installed the week of October 2nd.

Landscape restoration / installation of planting materials is also expected to begin next week.

Thanks again for all your patience as you dealt with the travel delays associated with the pavement milling process. Delays will continue as the work performed is primarily within the roadway. Please use caution and be patient.

Friday, September 15, 2017

Pavement Milling Next Week. Expect Travel Delays

Work Performed, September 11th to September 15th
·         Poured concrete sidewalk from River Drive to Church Street
·         Poured colored and stamped concrete sidewalk from River Drive to Church Street
·         Poured concrete driveways and sidewalks at public parking lot east of River Drive (next to Oil Lamp Theater). Access is now restored.
·         Lowering of manholes in preparation for pavement milling.
·         Continued with irrigation and street lighting installations along project site.

Work Anticipated to be Performed, September 18th to September 22nd
·         Milling existing pavement along Glenview Road from Harlem Avenue to Waukegan Road (Glenview Road and Harlem Avenue Project)
·         Perform patching of failed pavement sections as identified after milling.
·         Continue with installation of electrical and irrigation systems along project site.
·         Perform repairs to water main system identified during final testing.

On Monday and Tuesday next week, the contractor will be milling the existing pavement along Glenview Road from Harlem Avenue to Waukegan Road as part of the Harlem Avenue Improvement and the Glenview Road Improvements.  The work has been scheduled to be completed at the same time to reduce the length of travel delays. We do anticipate some travel delays along Glenview Road early next week while the work is on-going, please plan accordingly.

Concrete sidewalk work is nearly completed for the entire project with the exception of areas where the temporary traffic signal and light poles are in conflict.

We do anticipate the travel delays to be more significant during the roadway phase since the work will be performed primarily within the travel lanes in lieu of the sidewalks as performed previously. It is anticipated that the first layer of asphalt pavement will be installed the week of September 25th.

Thanks for your understanding and patience as you deal with the travel delays associated with the roadway improvements.