Work focused on the area between the railroad
tracks and Pine Street on the south side of the road (adjacent to Glenview
House)
o Removed
and poured concrete curb & gutter and sidewalk
o Completed
underground piping for irrigation and electrical systems.
o Poured
colored and stamped concrete sidewalk
o Majority
of work in this area is completed.
·
Poured colored and stamped concrete around
Veteran’s Memorial at River Drive
·
Poured colored and stamped concrete in various
medians.
·
Continued with installation of traffic signals
and posts at Glenview Road and Church Street
·
Continued with irrigation and street lighting
installations along project site.
Work Anticipated to be Performed, September 11th
to September 15th
·
Pour concrete sidewalk from River Drive to
Church Street
·
Remove temporary stone and pour concrete
driveways and sidewalks to public parking lot east of River Drive (next to Oil
Lamp Theater)
·
Continue with installation of electrical and
irrigation systems along project site.
·
Continue installation of new traffic signals at
Church Street and Glenview Road.
·
Begin setting new light poles.
·
Complete abandonment of old water main that is
no longer in service.
Next week, the concrete sidewalk and driveways for the
public parking lot on the south side of Glenview Road east of River Drive (next
to Oil Lamp Theater) will be poured. The parking lot will be closed starting on
Monday (September 11th) and re-open by Friday (September 15th).
Street parking along Glenview Road will be available during this time.
The concrete sidewalk improvements are nearly completed on
the south side of Glenview Road. It is anticipated a majority of the concrete
sidewalk, stamped and colored concrete sidewalk, and concrete curb & gutter
replacements will be completed by the end of the next week for the entire
project. The remaining concrete to be completed are those areas where the
temporary street lights and temporary traffic signal poles are in conflict.
With the concrete work nearly completed, the project will be
moving to the next phase, roadway resurfacing. It is anticipated roadway
resurfacing will begin the week of September 18th. Roadway
resurfacing will include removing the top 2-inches of the existing asphalt
pavement, performing repairs to the remaining pavement as needed, and installation
of a new asphalt surface. Glenview Road will remain open during this
construction; however, lanes will be reduced and flaggers will be present. We
do expect significant travel delays, so please plan accordingly.