Poured concrete sidewalk from River Drive to
Church Street
·
Poured colored and stamped concrete sidewalk
from River Drive to Church Street
·
Poured concrete driveways and sidewalks at
public parking lot east of River Drive (next to Oil Lamp Theater). Access is
now restored.
·
Lowering of manholes in preparation for pavement
milling.
·
Continued with irrigation and street lighting
installations along project site.
Work Anticipated to be Performed, September 18th
to September 22nd
·
Milling existing pavement along Glenview Road
from Harlem Avenue to Waukegan Road (Glenview Road and Harlem Avenue Project)
·
Perform patching of failed pavement sections as
identified after milling.
·
Continue with installation of electrical and
irrigation systems along project site.
·
Perform repairs to water main system identified
during final testing.
On Monday and Tuesday next week, the contractor will be
milling the existing pavement along Glenview Road from Harlem Avenue to
Waukegan Road as part of the Harlem Avenue Improvement and the Glenview Road
Improvements. The work has been scheduled to be completed at the same
time to reduce the length of travel delays. We do anticipate some travel delays
along Glenview Road early next week while the work is on-going, please plan
accordingly.
Concrete sidewalk work is nearly completed for the entire
project with the exception of areas where the temporary traffic signal and
light poles are in conflict.
We do anticipate the travel delays to be more significant
during the roadway phase since the work will be performed primarily within the
travel lanes in lieu of the sidewalks as performed previously. It is
anticipated that the first layer of asphalt pavement will be installed the week
of September 25th.
Thanks for your understanding and patience as you deal with
the travel delays associated with the roadway improvements.