Saturday, July 29, 2017

Work on North Side of Glenview Road Continues

Work Performed, July 24th to July 28th
·         Pour sidewalk, driveway, and curb & gutter in front of OLPH parking lot (one entrance only)
·         Continued to pour standard concrete sidewalk on the north side of Glenview Road from Church Street to bridge
·         Remove and pour sidewalk, driveways, and curb & gutter as needed on east side of Pine Street (one entrance will remain open at all times)
·         Poured colored and stamped concrete on east side of Church Street.
·         Installed irrigation piping
·         Continued with electrical installation for new street lighting.

Work Anticipated to be Performed, July 31st to August 4th
·         Continue to remove and pour standard concrete on north side of Glenview Road from Pine Street to Waukegan Road
·         Pour colored and stamped concrete on north side of Glenview Road
·         Remove and pour remaining driveway, curb & gutter, and sidewalk on east side of Pine Street
·         Remove and pour sidewalk, driveway, and sidewalk at remaining OLPH driveway.
·         Continue with irrigation piping installation
·         Continue with electrical conduit installation for street lighting

The construction is currently progressing as expected throughout the project site.  We are anticipating the work on the north side of Glenview Road will be completed in the next few weeks prior to the start of school for OLPH.  Once the work on the north side of the street is completed, work on the south side will begin.

Thanks again for all your patience and understanding.  Please remember, all businesses remain open during construction.

Friday, July 21, 2017

Concrete Sidewalk on North Side of Glenview Road Continues.


Work Performed, July 17th to July 21st  
·         Removed sidewalk on the north side of Glenview Road from Church Street to bridge
·         Poured standard concrete sidewalk on the north side of Glenview Road from Pine Street to Bridge
·         Installed irrigation piping
·         Install electrical conduit and began setting concrete posts for street lighting.

Work Anticipated to be Performed, July 24th to July 28th
·         Pour sidewalk, driveway, and curb & gutter in front of OLPH parking lot (one entrance only)
·         Continue to pour standard concrete sidewalk on the north side of Glenview Road from Church Street to bridge
·         Remove sidewalk, driveways, and curb & gutter as needed on east side of Pine Street
·         Pour sidewalk, driveways, and curb & gutter as needed on east side of Pine Street (one entrance will remain open at all times)
·         Complete storm sewer work
·         Remove and pour half the driveway near Jimmy John’s / Shoppers Row parking lot
·         Continue with irrigation piping installation
·         Continue with electrical conduit installation for street lighting
·         Pour concrete bases for street lights.

Thank you to all the business owners and patrons while accessing the businesses along Glenview Road during the construction.  The Village is committed to minimizing any inconvenience to the greatest extent possible.

Friday, July 14, 2017

Concrete Sidewalk Replacement Continues on North Side of Glenview Road from Pine Street to Bridge

Work Performed, July 10 – July 14:  
·           Removed sidewalk along business front on north side of Glenview Road from Pine Street to Church Street
·           Poured concrete sidewalk up to select business fronts on the north side of Glenview Road from Pine Street to Church Street

Work Anticipated to be Performed, July 17 – July 21
·           Remove old sidewalk on the north side of Glenview Road from Pine Street to Church Street
·           Access to businesses will be maintained with ramps and gravel walkway
·           Install unit duct and irrigation system
·           Once unit duct and irrigation installation is complete, pour new sidewalk, weather permitting
·           Remove and replace sidewalk on the east side of Church Street from Glenview Road to the alley
 
Thanks again for all your patience and understanding as you navigate through the construction zone and accommodate the work being performed.   

Friday, July 7, 2017

Construction Work Continues

Illinois legislators have passed a state budget, allowing construction of Glenview Road Streetscape Project to resume. Contractors will arrive onsite on Monday, July 10, 2017 and begin construction at 7:00 a.m.

In the next construction phase, the Contractor will be working to remove and replace the sidewalk on the north side of Glenview Road from Pine Street to Waukegan Road, then on the south side of Glenview Road from Waukegan Road to Church Street. Improvements also include irrigation system improvements; new street lighting; improved landscaping; stamped and colored concrete; traffic signal upgrades, and roadway repaving.

Coordination with business owners during construction is our highest priority. If you have any questions or concerns regarding the Glenview Road Streetscape Project, please feel free to contact Public Relations Representative Joanna Ptasinski at 815-444-3307 or jptasinski@glenview.il.us