Began Saw-cutting along limits of construction
·
Started installation of temporary street lights
·
Started installation of temporary traffic
signals at Church Street & Glenview Road
·
Mobilization of equipment
·
Material deliveries
Work anticipated to be performed Next Week, June 12th
to June 16th
·
Set-up full roadway closure of Glenview Road
from east of the bridge to Waukegan Road
·
Set-up detour route utilizing Waukegan Road,
Dewes Street, and Harlem Avenue
·
Install construction fencing within the roadway
around staging area from Shoppers Row / Oil Lamp Theater to Waukegan Road.
Sidewalk will remain open to pedestrians.
·
Begin water main construction
·
Begin storm sewer construction
·
Begin concrete sidewalk removal on west end of
project near railroad tracks.
We appreciate all your patience and understanding.