- Removal of concrete sidewalk and curb & gutter on
south side of Glenview Road from River Drive to Church Street
- Excavation for pavement widening from River Drive to
Church Street
- Poured colored and stamped concrete sidewalk across
bridge
- Poured standard concrete at Veteran’s Memorial near
River Drive
- Installation of irrigation piping from Church Street to
Waukegan Road
- Installation of underground electrical conduit from Waukegan Road to River Drive
Work Anticipated to be Performed, August 28th
to September 1st
- Pour concrete sidewalk adjacent to buildings on the
south side of Glenview Road from River Drive to Waukegan Road
- Pour colored and stamped concrete sidewalk from River
Drive to Waukegan Road
- Pour concrete curb & gutter from River Drive to
Church Street within pavement widening area.
- Continue with irrigation piping installation.
- Continue with underground electrical conduit
installation
- General site clean-up in preparation for Labor Day
weekend.
It is anticipated most of the concrete will be poured from
Waukegan Road to River Drive prior to the Labor Day Weekend. After Labor Day
Weekend, the contractor will focus on the pavement widening between River Drive
and Chruch Street as well as the area west of the Mid-Town Square Development
to the railroad tracks. Once all the concrete curb & gutter and
sidewalk is completed, the contractor will begin the roadway resurfacing phase
of the project.
Tentatively, the Municipal parking lot next to the Oil Lamp
Theater is scheduled to be closed starting Monday September 11th for
approximately 4 days. This will allow for residents and customers to park along
the street within this block while the parking lot is closed.
Thanks again for all your patience and understanding as we